Task

  Start

  End

  Cost

  Duration

Resources

Architectural design                    
2/1/11
5/6/11
E-mail CDB
68 work days
Draft design
2/1/11
2/17/11
E-mail CDB
12 work days
MST
Prepare documents
2/17/11
3/9/11
E-mail CDB
14 work days
Jose Herrasti
Submit plans
5/5/11
5/6/11
E-mail CDB

Jose Herrasti
Interior design
2/17/11
3/10/11
E-mail CDB
15 work days
Pre-design
2/17/11
2/24/11
E-mail CDB
5 work days
MST
Furniture selection
2/24/11
3/3/11
E-mail CDB
5 work days
MST
Equipment planning
3/3/11
3/10/11
E-mail CDB
5 work days
MST
Construction phase
5/6/11
2/22/12
E-mail CDB
208 work days
Gary Daly
Clearing
5/6/11
6/17/11
E-mail CDB
30 work days
Gary Daly
Roof
6/17/11
9/9/11
E-mail CDB
60 work days
Gary Daly
Structural
9/9/11
12/2/11
E-mail CDB
60 work days
Gary Daly
Plumbing
12/2/11
1/13/12
E-mail CDB
30 work days
Gary Daly
Electric
12/2/11
1/13/12
E-mail CDB
30 work days
Contractor
HVAC
12/2/11
1/13/12
E-mail CDB
30 work days
Contractor
Information network
12/2/11
1/13/12
E-mail CDB
30 work days
Contractor
Dry walls
1/13/12
2/2/12
E-mail CDB
14 work days
Contractor
Equipment installation
2/2/12
2/22/12
E-mail CDB
14 work days
Contractor
Construction complete
1/13/12
1/14/12
E-mail CDB
Decoration phase
2/22/12
3/23/12
E-mail CDB
22 work days
Walls
2/22/12
3/13/12
E-mail CDB
14 dwork days
Contractor
Furniture
3/13/12
3/22/12
E-mail CDB
7 work days
MST
Marketing and management
3/22/12
3/23/12
E-mail CDB
MST
.
Total Project
2/1/11
3/23/12
E-mail CDB
298 work days